We did 6 parts aggregate (melange or mix they call it at the quarry - 4 parts gravel to 2 parts sand) to 1 part cement and just less than one part water. 1 part was 8 liters.
15 mixers full = 90 buckets of aggregate +
15 buckets of cement (which was 5x35kg bags) +
15 buckets of water
We added water then 3 parts of aggregate then the cement then the other 3 aggregate and mixed for 3 mins. Resulting in a total of 30 wheelbarrow fulls of cement that all had to be tipped in and tamped down and leveled.
We are both KNACKERED!! And there is still the other half to go... and the garage and the outdoor kitchen and the whole house. Aaaaaaargh.
Aargh too dry add more water |
Pouring it - hopefully not too dry now! |
Mixing it up |
Finishing touches |
No comments:
Post a Comment